Refer to Rule 3. C. (vi). The online bid form usually allows you to define whether you have or have not included a cash allowance. However, under the BOBS Rules if it is specified only in your Section or Division of work, or you are instructed to include it, then you are required to include it in your bid. Therefore, if you are required to include it and you did not the General Contractor can assign you the cash allowance to you. They must add the value of the cash allowance to your contract amount but they are not required to pay you any markup to carry the cash allowance; that markup should have been part of the bid.